Fire Fighting System Göta Tunnel

08/09/2017

Actemium Automation har recieved an order from Acobia Flux och Trafikverket for installation of a new fire fighting system in the Göta tunnel in Gothenburg.

Actemium will perform electrical design as well as electrical installation and Acobia will perform programming of PLC as well as integration into existing SCADA.

The comissioning will be in cooperation between Acemium and Acobia and will take place i two phases:

Phase 1 – South tunnel tube in the end of January 2018
Phase 2 – Nothern tunnel tube in the end of April 2018

Manufacturing of control cabinets will take place in October – November 2017

The project will be completed in July 2018.