Actemium takes care of the electrical and instrumentation installations for the new Marieholm bridge

23/06/2014

Actemium has been assigned by the Skanska/MTH group to execute the electrical and Control installations for the swing bridge next to the existing Marieholm bridge.

The Project also includes rearming of the existing bridge with new surveillance and new PLC system similar to the one that is being installed on the new bridge.

We will also execute planning, design and programming of Siemens S7-400H as well as image construction in operator panels and SCADA (IFix).

The Project includes approx. 6 500 engineering hours and 4 000 mounting hours. The equipment will also be shipped to Poland for a complete test with hydraulic, machinery, electrical and control system as well as bridge superstructure.